< back

(Master and) Sub Plan History Source

RETURN TO: History Source

SPECIAL NOTES

Click History > Sub Plan History Source from the side navigation menu to apply a Master Plan as the History Source by sub plan.

SPECIALSelect NOTESType of History Source

If you choose Import from Existing Plan, also select Company, Establishment, and Plan from the drop-downs, which display only Master Plans as potential sources. Then select to have sub plans match the History Source by either:
  • Plan Code

OR

  • Establishment

  • By default, if the system does not locate a match, Manual Input will be required for each sub plan. To change this default, check the box for: Assign start point for all selected plans that do not have a match.

If Manual Input is selected in the Master Plan: Enter values into each sub plan to obtain accurate Goals and Adverse Impact reporting.

Assign Settings to Sub Plans

Expand the Sub Plans menu in the lower portion of the page.

Check off one or more sub plans, and click [Assign].

Quick Tip: If the setting applies to all sub plans, click the link at the top of the list to Select: All.