  • About the Sub Plan History Source
  • Sub Plan Considerations when Importing the History Source from an Existing Plan
  • Assign Settings to Sub plans


Set the History Source by Sub plan

About the Sub Plan History Source

MostAfter likely,developing Plan youCodes willand haveimporting appliedand validating Data Tables, the History Source, selected at plan creation, to all sub plans associated with the Master Plan.

However, if you need to make adjustments for one or more sub plans, choose History > Sub Plan History Source fromcan thebe sidedetermined navigationor menu.developed. The options for developing a source are the same as those for the MasterRegular Plan:plan:

  • Import from Existing Plan
  • Start Point Analysis (if a prior plan is not available)
  • Manual Input

The History Source for sub plans must be determined in the Master Plan. The module is not available within a sub plan.

Sub plan Considerations when Importing the History Source from an Existing Plan

When selecting Company, Establishment, and Plan, only Master Plans will display as potential sources.

An extra menu will ask whether sub plans should match the History Source by:

  • Plan Code
  • OR

  • Establishment

By default, Manual Input will be required for each sub plan lacking a match. To change this default, check the box for: Assign start point for all selected plans that do not have a match.

Assign Settings to Sub plans

Most likely, you will apply the same History Source to all sub plans associated with the Master Plan.

First, Expand the Sub Plans menu in the lower portion of the page to display a checklist of sub plans. All sub plans are checked by default.

Include the appropriate sub plans, and click the [Assign] button.