KEY TOPICS:

  • Add Feeders
  • Read Feeders from Promotions and Transfer Data
  • Assign Feeders by Job Group
  • Import Feeders from an Existing Plan or External File
  • Feeders in a Master Plan
    • Select Feeders from another Plan
    • Cascade to Sub plan

Identify Feeder Jobs to Determine Internal Availability

About Internal Availability

Internal Availability is a calculation, which involves determining what internal positions at your organization form a pathway for promotion (or transfer) from a source Job Group into a target Job Group. As part of this analysis, jobs that feed other jobs must be determined. A feeder can be defined as a "staffed position that provides a normal path into a higher-level Job Group," although transfers may also be included in making the determination.

Add Feeders

From the Internal Availability screen, select a target from the Job Group drop-down. If there are any feeders already assigned to this group, they will be displayed.

Choose [Add] from the upper toolbar, and a list of potential Feeder Job Codes will display for the Current Job Group. At the top of the menu: Select a Feeder Job Group, which will be the source of feeders.

After checking one or more Job Codes, and click [Add Feeders].

Notes: At least one Roster employee must be assigned to the Job Code/Title before the position can be designated as a feeder.

Feeders will typically not be assigned for entry-level Job Groups.

Example: You may select feeders from different source Job Groups: Target Job Group 1B may have feeders from source Job Group 2A and 3A.

Repeat these steps for each Job Group.

Read Feeders from Promotions and/or Transfers

balanceAAP can identify feeders from the Promotions (and Transfer) data.

Click [Read Feeders] in the upper toolbar to access this function. Select the appropriate options as follows:

  • Read Feeders from Promotions or Transfers – Select one or both tables. The job code the employee moved from will be added as a feeder to the job group of the job code they moved to.
  • Apply to Current Job Group or All Job Groups – Select whether you want the function to apply to all job groups in your plan, or only the job group currently set as the target group.
  • Append Append(Add to existing) or Overwrite (Replace existing) – Select Append if you already have feeders assigned to groups that should not be lost. Select Overwrite, and any existing feeders will be replaced with the feeders added by the function.

Once the selections are made, click [Apply].

Import Feeders from an Existing Plan or External File

Click [Import]. Choose one of the following:

  • From an Existing Plan – Choose Company, Establishment, and Plan from the drop-downs.
  • From an External File –

If you selected the From an External File, choose a file type from the drop-down list from Excel, Access or a text file. NOTE: If your file is in Excel or Text format, you have the option to indicate if the first row in the file contains column headers. Also, if your file is in Text format, select the appropriate field delimiter from the drop-down list. Click Browse to select the file and click Next.

Select a file and the appropriate file options (e.g. spreadsheet, table name, etc.). You will then be prompted to match your fields. A preview of the data to be imported will be displayed. Click Next when completed. Click Import to complete the import process.

Feeders in a Master Plan

Select Feeders from Other Plans

When jobs from one location/sub plan can be considered feeders for another sub plan, feeders can be selected from those plans.

Choose [Feeder Options] from the upper toolbar. Check the box for: Allow feeders to be selected from other plans.

Choose Company, Establishment, and Plan from the drop-downs. Proceed to assigning feeders in the same manner as described above.

Cascade to Sub Plan

The following function can be cascaded to sub plans, using a check box at the bottom of the page:
  • Read Feeders from Promotion (and Transfer) Data

The following Additional Internal Availability Toolsalso have cascade options:

  • Remove Downward Movement
  • Feeder Job Weights